9/3/09 - James Pierotti wins election to the District's Board of Commissioner (5-year term); Andy Lindquist re-elected to Treasurer (3 year term); Proposition to eliminate the need for a District Permit for work on break walls in favor of supporting the currently required DEC permit process is defeated. 

8/17/09 - $5.3 million Stimulus check issued to Town of Cuba for Sewer Project.  Click here for pictures.

7/14/09-Blue Heron is on the move, directional drilling and pipe make-up is almost complete for the first 700 feet. See Pics!

7/6/09 - Blue Heron Construction Horizontal, Directional Drilling Pictures posted.  Pictures taken in lot adjacent to Five Star Bank in Cuba. See Pics!

6/24/09 - Cuba Lake District Board of Commissioners in a unanimous vote, canceled plans to continue legal action on the Town of Cuba tax reval due to the significant actions taken by the Town's Board of Assessment Review.

6/5/09 - Town and Village of Cuba get $7.4MM in stimulus funds for sewer projects.  Sewer Project - Stimulus Funds 6/5/09

More on Stimulus - 2nd Round Stimulus Announcement; Stimulus 2nd Round Fact Sheet

6/1/09 - Town of Cuba tax reassessment is lead story in District Dispatch.

5/9/09 - Town of Ischua holds meeting to present their plan for reassessment.

4/28/09 - At the bid opening for the Town of Cuba's District #5, Cuba Lake - 305 Corridor Sewer Project the low bid was $3,147,240.20; the high bid was $5,989,000. Click here to see more.

4/27/09 - Refuse pickup begins Monday, May 4, 2009 and ends Monday, October 26, 2009.  Recyclables are picked up every week on the same schedule except as noted below.  Put all items out by 7:00 AM the morning of collection.  Click here for complete details.

LARGE REFUSE TYPE MATERIALS WILL BE COLLECTED-

THE FIRST MONDAY IN JUNE 2009 AND,

THE LAST MONDAY IN AUGUST 2009. 

NOTE:  THERE WILL BE NO RECYCLING ON THE DATES OF LARGE REFUSE PICKUP.

4/27/09 - On the Sewer Project -

 

Link to E/one http://www.eone.com/extreme/products.htm.

 

 

8/30/08 - Running unopposed, Gerald Collins is elected to a second, five year term as Commissioner on the Cuba Lake District Board of Commissioners.  44 voters turned out to show their support of Jerry and of the District Elections.  Officials overseeing and certifying the election were Susan & Larkin Gram (Noon to 4:00 PM shift); Dian & Siegfried Rieder  (4:00 PM to 8:00 PM shift).

6/10/08 - Contractor updates Sewer District #5 status at Town of Cuba Meeting.  See Comments.

2/14/08 - Towns of Cuba & Ischua Sewer Project:

The Towns of Cuba and Ischua began the public interaction part of the newly formed sewer districts' waste collection project.  Letters will be issued by February 16th to those owners within the sewer districts who “own” developed property.  Developed property includes those parcels of land within the sewer districts that have dwelling units or public or commercial facilities.  The letter briefs the next steps in the process and provides for feedback from those involved to agree to hookup to the sewer; to provide for the necessary work and maintenance easements on the property or properties as the case may be; and, to provide for feedback to enable locating the grinder pump package on the property.  Agreements and feedback are required to be mailed by Midnight, March 17, 2008.

A copy of the letter can be viewed HERE. And a sample feedback form with aerial photo can be viewed HERE.

Note that on properties having multiple owners listed, the mailing has been sent to only one address and an answer received will be understood to represent the wishes of all parties to the leasehold or deed.  The form provides space to establish who the contact for making installation decisions will be for the property in question.

Note also that while only one property is identified by tax number on the form, the agreement for work permits includes those properties also owned by the same party addressed that fall between the road (path of the sewer mains) and the property identified by specific tax number.  It will be necessary to have easements from the point of attachment to the sewer main from the point of location of the grinder pump.

Obviously, if the decision is made to hook up to the sewer, the easements must be agreed to.

Any questions should be directed to Clark Patterson Lee Design Engineers, Tom Swift @ (800) 274-9000, ext. 1401.

 

 

12/28/07 - Mount Monroe:

Contract Let to LDC Construction, Grand Island, NY. for $113,339.

DEC final go-ahead was received December 26th.

The Lake Manager and Clark-Patterson met at site on Friday, December 28th to finalize actions needed to begin work.

Target Completion date is May End 2008.

 

12/28/07 - Forms required for use in the Permit process associated with the Land Use Restrictions and Controls (LUR) have been updated to reflect the requirements of the last LUR (August 2006) adopted by the District's leaseholders and owners.  Also, the forms may now be completed on-line and printed or filed to your computer.  Forms can be found HERE!

 